How Does the Construction Act Affect Invoice Finance?

The Housing Grants, Construction and Regeneration Act 1996 (Construction Act) gives subcontractors the right to stage payments, payment notices, and adjudication. Specialist construction factoring providers understand these mechanisms and advance against certified applications for payment, not just standard invoices. Pay-when-paid clauses are banned except on insolvency.

Why This Matters

The Housing Grants, Construction and Regeneration Act 1996 (as amended in 2011) fundamentally changed how UK construction businesses get paid, and that directly affects how they finance receivables. Unlike a standard invoice finance arrangement where funds release against invoices with fixed terms, construction firms work with payment applications, retention clauses, and interim certificates.

This creates complexity: a Birmingham groundworks contractor might have £180,000 certified on an application but only receive £171,000 (5 percent held as retention), and payment depends on the main contractor issuing a payment notice within five days. Specialist construction factoring providers advance against these certified applications, not final invoices, because cash flow gaps on 60-90 day certified payments can cripple a subcontractor paying weekly wages.

The Act also banned conditional payment clauses (pay-when-paid), meaning funders can rely on the statutory payment timeline. Specialist construction funders assess certified applications, retention release schedules, and adjudication risk when setting advance rates.

Many generalist invoice financiers decline construction receivables or advance less against them, so for a small subcontractor, choosing a funder unfamiliar with the Construction Act can mean rejection or a much lower advance than a specialist would offer against certified sums.

Key Points

Illustrative Example

Hypothetical: a Leeds-based electrical subcontractor with £900,000 annual turnover submits a monthly payment application for £65,000 to a main contractor working on a hospital refurbishment. The architect certifies £62,000 after £3,000 is held as retention (just under 5 percent), and the contract specifies payment 21 days after certification. The subcontractor has a weekly wage bill of £8,500 and needs cash within five days.

The subcontractor factors the certified application through a specialist construction funder, which advances 85 percent of the certified £62,000 (£52,700) within 48 hours of certification, holding £9,300 in reserve. On day 21, the main contractor pays the £62,000 gross, the funder releases the reserve minus fees (discount charge of 0.6 percent per week on £62,000 for three weeks totals roughly £1,116, plus a £300 service fee), and the subcontractor nets the balance.

At practical completion six months later, the £3,000 retention is released and the funder advances 80 percent (£2,400) immediately, with the remainder following once cleared. These figures are illustrative, not a real client case or any provider's actual terms.

Common Pitfalls

What to Do Next

Related Questions

Can I factor a payment application before the architect or engineer certifies it?

No. Invoice finance providers require a certified application (certificate, interim valuation, or payment notice) as proof the sum is due. Uncertified draft applications carry too much variation risk. Some funders will pre-approve an application subject to certification, allowing same-day release once the certificate arrives, but no advance occurs without third-party verification of the amount due.

What happens if the main contractor disputes the certified amount and issues a pay-less notice?

A valid pay-less notice (issued within the timeframe specified in the contract, typically five days before payment is due) reduces the sum immediately payable. The funder will freeze or reduce the advance to match the undisputed portion. You must then pursue adjudication under Section 108 to recover the disputed balance. If you win adjudication, the funder releases the additional amount once the debtor pays the adjudicator's decision.

Do construction invoice finance providers charge CIS tax as a debtor risk?

No. CIS (Construction Industry Scheme tax deductions) is withheld by the main contractor and paid directly to HMRC, reducing the net payment to you. Funders advance against the gross certified amount but reconcile to the net payment after CIS deduction. You remain liable for the reserve difference if the debtor deducts CIS at 30 percent (unregistered subcontractors) instead of the expected 20 percent. Ensure your CIS registration is current to avoid funding shortfalls.

AP

Adam Parker

Founder & Managing Director, Muswell Rose, founder and PSC of Best Business Loans Ltd

Adam is the founder and managing director of Muswell Rose and a founder of Best Business Loans Ltd, the company behind Market Invoice. He spent over three years as managing director of Penny, a UK invoice finance business, and his career runs through insurance, mortgages, commercial finance and fintech lending. He writes the Market Invoice library.

Last updated:

Get 3 Free Invoice Finance Quotes

Free, no obligation. Tell us about your business and eCapital, our introduction partner, handles your enquiry and comes back to you with quotes.

Step 1 of 3 · Your business

Start typing and we'll search Companies House.

Free to you: our introduction partner pays us a fixed fee for each introduction, whether or not you go ahead. See our privacy policy.

Free · No obligation · Nothing to pay us

How we make money: Market Invoice is an independent comparison service, not a lender. Our introduction partner pays us a fixed fee for each business we introduce, whether or not you go ahead; you never pay us and it is never added to your costs. How we are funded.